Project Schedule and Key Dates for Warriors new Arena in SF Reviewed by Momizat on . The official details and key dates of the Warriors proposed new Arena in San Francisco are now emerging, as reported by SocketSite.com. ∙ October 2012: Homeowne The official details and key dates of the Warriors proposed new Arena in San Francisco are now emerging, as reported by SocketSite.com. ∙ October 2012: Homeowne Rating:
You Are Here: Home » News » Project Schedule and Key Dates for Warriors new Arena in SF

Project Schedule and Key Dates for Warriors new Arena in SF

The official details and key dates of the Warriors proposed new Arena in San Francisco are now emerging, as reported by SocketSite.com.

∙ October 2012: Homeowner Association Meetings and Public Outreach
∙ October 16, 2012: Conceptual Drawings, Framework and Fiscal Feasibility Presentation
∙ October 23, 2012: Port Commission Action on Framework and Fiscal Feasibility
∙ November 20, 2012: Board of Supervisors Action on Framework and Fiscal Feasibility
∙ November 21, 2012: Notice of Preparation for EIR issued by Planning Department
∙ December 2012 thru 2013: Bay Conservation and Development Commission (BCDC)
Design Review Board (DRB) Hearings
∙ January/February 2013: Port Commission Hearing and Action on Term Sheet
∙ January/February 2013: Board of Supervisors Action on Term Sheet
∙ Summer 2013: Planning Commission Hearings: Environmental Impact Report (EIR)
∙ Late Fall 2013: Certification of EIR; adoption of Zoning and General Plan
Amendments and approval of Conditional Use permits if required
∙ January – April 2014: Board of Supervisors Action on Transaction Document
∙ January – April 2014: BCDC DRB Action on Project Design
∙ January – April 2014: BCDC Major Permit & Public Trust Consistency
∙ January – April 2014: Other regulatory approvals
∙ Summer 2014: Proposed Start Construction
∙ Summer 2017: Proposed Complete Construction

You can read the full article, HERE.